Construction progress photos

July 2021

Ongoing facade installation, elevated walkway construction

June 2021

Facade installation


May 2021

Internal fit-out, roofing, elevated walkway installation


March 2021

Concrete pours on levels 7-8, internal fitout and ongoing construction of elevated walkway.


February 2021

Concrete pours for levels 6-7, installation of frames for elevated walkway.


January 2021

Columns, form work and concrete pours for levels 5-6.

June 2021


November 2020

Columns, form work and concrete pours for levels 3-4.


October 2020

Columns, form work and concrete pours on the first three levels

May 2021


September 2020

Crane set-up, lift shafts and initial concrete pours


August 2020

Initial site set-up