We're building a bigger and better Logan Hospital to provide more healthcare services for the local community.

206 additional beds and treatment spaces
4 new floors + building-in of ground floor level
1506 new car parking spaces
5 additional birthing suites

Keep up-to-date

Register for updates

Latest news

Logan Hospital crane named "Sir Lift-a-Lot"

The 38.9-metre tower crane on the site of Logan Hospital’s new multi-level car park has officially been knighted as "Sir Lift-a-Lot".

Name the crane

Vote now—help name the crane that's building our car park

Primary school kids throughout the region have risen to the challenge of naming the 38.9-metre high crane that’s building Logan Hospital’s new multi-level car park.

Timeline


Early

2020

New medical ward (Ward 2M) opened
New Mental Health Lounge opened

Mid

2020

Detailed design for major expansion commenced
Construction started on Multi-level Car Park

Late

2020

Critical infrastructure upgrades completed

Early-mid

2021

Maternity Refurbishment construction starts
We are here

Mid-late

2021

Construction starts on Building 3 vertical expansion
Multi-level Car Park opens

 

2022

Building 1 refurbishment works start

 

2023

Progressive opening of services in Building 3 vertical expansion

 

2024

All building works and commissioning complete

Timeline is subject to change

What we're building

ED Mental Health Lounge Logan Hospital Expansion - Building 3 Logan Hospital Expansion - Building 1 Logan Maternity refurbishment 28-bed Medical Ward Logan Hospital Expansion - Building 2 Multi-level Car Park